Phase 2

Nano-Grid Network Joining

From mini-sub mapping through nano-grid design, equipment ordering and deployment, ending with ongoing monitoring and evaluation.

  1. T0 + 12 Days

    Mini-sub mapping

    Use the Per Street Report (PSR) to conduct mini-sub mapping.

  2. T0 + 13 Days

    Complete nano-grid design

    Finalise the nano-grid design based on the mapped mini-subs and ward data.

  3. T0 + 15 Days

    Commence equipment ordering

    Begin ordering the equipment required for the designed nano-grids.

  4. T0 + 20 Days

    Install QoS meter & record baseline

    Install the QoS meter at the mini-sub and record the baseline QoS profile.

  5. T0 + 25 Days

    Start deployment

    Commence the physical deployment of nano-grids across the wards.

  6. T0 + 30 Days

    Commence monitoring & evaluation

    Begin monitoring and evaluation (M&E) of the deployed nano-grid network.