Phase 2
Nano-Grid Network Joining
From mini-sub mapping through nano-grid design, equipment ordering and deployment, ending with ongoing monitoring and evaluation.
- T0 + 12 Days
Mini-sub mapping
Use the Per Street Report (PSR) to conduct mini-sub mapping.
- T0 + 13 Days
Complete nano-grid design
Finalise the nano-grid design based on the mapped mini-subs and ward data.
- T0 + 15 Days
Commence equipment ordering
Begin ordering the equipment required for the designed nano-grids.
- T0 + 20 Days
Install QoS meter & record baseline
Install the QoS meter at the mini-sub and record the baseline QoS profile.
- T0 + 25 Days
Start deployment
Commence the physical deployment of nano-grids across the wards.
- T0 + 30 Days
Commence monitoring & evaluation
Begin monitoring and evaluation (M&E) of the deployed nano-grid network.