Master timeline
Master 30-Day Timeline
T0 = Project Kickoff. A single coordinated pathway from kickoff through Phase 1 (Account On-Boarding) and Phase 2 (Nano-Grid Network Joining) to monitoring and evaluation.
Phase 1: Account On-BoardingPhase 2: Nano-Grid Network Joining
051015202530
- Identify wards & per-street engagement planT0 + 3
- Submit plan & obtain approvalT0 + 4
- House visits (education & roof assessment) per wardT0 + 5 to 9
- Transfer Per Street Report (PSR) to Electrical Dept.T0 + 10
- Complete system updates (MyMunic + Municipal)T0 + 15
- Use PSR to conduct mini-sub mappingT0 + 12
- Complete nano-grid designT0 + 13
- Commence equipment orderingT0 + 15
- Install QoS meter & record baseline QoS profileT0 + 20
- Start deploymentT0 + 25
- Commence monitoring & evaluation (M&E)T0 + 30
Key milestones
T0
Kickoff
T0 + 3
Plan Created
T0 + 4
Approval Obtained
T0 + 10
PSR Handover
T0 + 12
Mapping
T0 + 15
System Updates & Ordering Commence
T0 + 20
QoS Baseline Recorded
T0 + 25
Deployment Starts
T0 + 30
M&E Commences