Master timeline

Master 30-Day Timeline

T0 = Project Kickoff. A single coordinated pathway from kickoff through Phase 1 (Account On-Boarding) and Phase 2 (Nano-Grid Network Joining) to monitoring and evaluation.

Phase 1: Account On-BoardingPhase 2: Nano-Grid Network Joining
051015202530
  • Identify wards & per-street engagement plan
    T0 + 3
  • Submit plan & obtain approval
    T0 + 4
  • House visits (education & roof assessment) per ward
    T0 + 5 to 9
  • Transfer Per Street Report (PSR) to Electrical Dept.
    T0 + 10
  • Complete system updates (MyMunic + Municipal)
    T0 + 15
  • Use PSR to conduct mini-sub mapping
    T0 + 12
  • Complete nano-grid design
    T0 + 13
  • Commence equipment ordering
    T0 + 15
  • Install QoS meter & record baseline QoS profile
    T0 + 20
  • Start deployment
    T0 + 25
  • Commence monitoring & evaluation (M&E)
    T0 + 30

Key milestones

T0

Kickoff

T0 + 3

Plan Created

T0 + 4

Approval Obtained

T0 + 10

PSR Handover

T0 + 12

Mapping

T0 + 15

System Updates & Ordering Commence

T0 + 20

QoS Baseline Recorded

T0 + 25

Deployment Starts

T0 + 30

M&E Commences